Topic Options
#16202 - 03/03/09 11:17 AM Interest Aging - A/R
fishers Offline
Stranger

Registered: 02/27/09
Posts: 4
Loc: Canada
To make the question simpler:

When I create an interest batch in Adagio Receivables the interest batch which is created has a due date the same as the invoice date.

How do I make the interest batch have a due date the 25th of the following month?
_________________________
-LA

Top
#16203 - 03/03/09 11:52 AM Re: Interest Aging - A/R [Re: fishers]
Bruce Gardner Offline
Adagio Wizard

Registered: 06/15/04
Posts: 3613
Loc: Toronto ON, Canada
Hello Fishers:

You could manually edit the Due Dates in the batch. That works OK for a small number of invoices, admittedly not so well for a larger number.

The concept is that the interest charges are due immediately, not at a later date. That's pretty standard. There's probably a good reason why your firm gives terms on interest due but could you explain it for us?
_________________________
Bruce Gardner
ARX Business Solutions Inc.

Top
#16237 - 03/05/09 12:26 PM Re: Interest Aging - A/R [Re: Bruce Gardner]
fishers Offline
Stranger

Registered: 02/27/09
Posts: 4
Loc: Canada
You were correct in saying that interest charges are due immediately. I made a preliminary assumption based on initial discrepancies between the old AccPac statements and the new Adagio statements.

Thanks for your help. I did initially try to manually change the dates although it did not seem to keep the dates I changed them to.
_________________________
-LA

Top


Moderator:  Christa_Meissner 
Who's Online
1 registered (1 invisible), 120 Guests and 0 Spiders online.
Key: Admin, Global Mod, Mod
Forum Stats
1865 Members
5 Forums
14467 Topics
70662 Posts

Max Online: 432 @ 01/20/25 10:17 PM
April
Su M Tu W Th F Sa
1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30