When a job needs to be revised ie: Original cost to customer is $4050.00.
Original Estimated costs are: Product "1" is $1000.00. Product "2" is $1000.00.
Product '3" is $1000.00. Customer changes their mind and cancels product 3.
Total cost to customer is now $2700.00.
To make the changes in Job Cost to reflect the cancellation of part of the job....
Step 1. In Job Cost, we create a change order for -$1350.00.
In estimates, do we change the current estimated cost to "0" for product 3?
I'm questioning this because that's what I did today, but when I printed the
Job Estimates Audit report it shows the job estimate as a negative dollar
amount.
If this is the correct procedure, great, if not, please let me know how to input the changes properly.
Thanks so much!
Karen