Hi,

I have done an upgrade from AR9.1A (130606) to AR9.2A.
I have also upgraded LanPak, Ledger, Payables and GridView to 9.2A.

When I start Ledger, Payables or Receivables I get a WARNING. Your Workstation is not Up-to-date!

Since I did the upgrade from my workstation, I'm not sure why it's complaining. I even renamed the softrak folder on my C:\ Drive to Softrak-TEST, did a new WKSETUP of Receivables which works fine (other than a Crystal issue) but when I launch from the shortcut on my desktop, i get the warning again...

NOTES:
The Crystal issue is raleted to the fact that I have a newer DLL
I have disabled UAC.
This is not a PRODUCTION Setup, i've learned my lesson... This is on a TEST system currently

Any help would be appreciated.

Top
#47528 - 10/07/15 12:29 PM Re: 9.2A Upgrade Loop [Re: Yann]
Yann Offline
Adagio Scholar

Registered: 10/26/06
Posts: 94
Loc: BC, Canada
Ok,

I think I resolved it...

As noted above, I had a newer Crystal Reports Runtime on my system than Adagio tries to install.
9.2A installs 13.0.9.1312 and I had 13.0.13.1597

I uninstalled my Crystal Runtime, ran the WKSETUP for Receivables and it installed properly.

Hope this helps anyone else how runs into this.

Top


Moderator:  Christa_Meissner 
Who's Online
0 registered (), 26 Guests and 1 Spider online.
Key: Admin, Global Mod, Mod
Forum Stats
1848 Members
5 Forums
14242 Topics
69746 Posts

Max Online: 359 @ 11/18/19 09:08 PM
May
Su M Tu W Th F Sa
1 2 3 4
5 6 7 8 9 10 11
12 13 14 15 16 17 18
19 20 21 22 23 24 25
26 27 28 29 30 31