Hello:
Let's say we have a product composed of 5 components in the BOM. When entering the components into the Bill of Materials screen of Adagio, it allows entering two fields at a "higher Level".
(A) Cost to Prorate
(B) Additional Cost
These two cost fields are actually stored in the table ICBillOfMaterialListHeader in fields with these names:
(A) Fixed Assembly Cost
(B) Variable Assembly Cost
Most of our products don't use those fields. But there are a few older products that do. When we add up the component costs from the values in the ICItems123Master, they agree with the sum of the component costs. For some reason, the Cost to Prorate and Additional Cost are NOT added to the product cost. What do those two fields do...nothing?
Thanks,
_________________________
Rich Locus
Marco Pharma, LLC