#49537 - 04/07/16 12:54 PM
Manual proration of MC in PO 9.2A
|
Adagio Scholar
Registered: 05/07/06
Posts: 97
Loc: Toronto, ON, Canada
|
Hi All,
We just migrated Adagio to 9.2 platform. I could not figure out how to process manual proration of misc. charges when processing receipt in PO (9.2A). On the receipt we have 2 vendors: actual vendor we receive items from and artificial vendor to process estimated landed cost components. MC defined in MC table: Freight - manual proration, Brokerage - by relative value.
Please recommend me in simple bullet point form how to process this type of receipt.
Any help will be greatly appreciated. Victor
_________________________
Victor
|
Top
|
|
|
|
#49543 - 04/07/16 07:40 PM
Re: Manual proration of MC in PO 9.2A
[Re: Victor B.]
|
Adagio Scholar
Registered: 05/07/06
Posts: 97
Loc: Toronto, ON, Canada
|
Hello,
I have an additional update of this problem: 1. Upgraded PO to 9.2B 2. Item vendor currency - $USD, Misc. charges currency - $CAD 3. Misc. charge that require proration by relative value calculated properly. If I add misc. charge that require manual proration I have to edit line item calculate and add manual proration amount to "Allocated misc." field. 4. After pressing "Post" button error message appears: "Manual allocation of miscellaneous charge for 888.77 was allocated to 1155.40. Edit items and update: Allocated misc." ????????
Can anyone explain to me how to process this transaction properly.
Regards Victor
_________________________
Victor
|
Top
|
|
|
|
#49545 - 04/08/16 07:23 AM
Re: Manual proration of MC in PO 9.2A
[Re: Victor B.]
|
Adagio Master
Registered: 03/16/99
Posts: 10504
Loc: Canada
|
Hello Victor,
I don't think that there is a "proper" way to process this receipt, which might explain why there has been no feedback. Adagio PurchaseOrders offers several ways to prorate additional costs because different companies have different business needs.
From the numbers in your second post, I would guess that you have a negative receipt quantity in one of the lines, but I might be mistaken.
Since you upgraded from a previous version, I'm also guessing that you have not changed the way you previously posted receipts. In re-writing Adagio PurchaseOrders, we found many calculation irregularities in Receipt Processing and especially additional cost handling in Purchase Orders for Adagio.
Perhaps you should review your receipt processing method with an Adagio Consultant.
_________________________
Andrew Bates
|
Top
|
|
|
|
#49613 - 04/13/16 05:39 PM
Re: Manual proration of MC in PO 9.2A
[Re: Softrak Support]
|
Adagio Scholar
Registered: 05/07/06
Posts: 97
Loc: Toronto, ON, Canada
|
Hi All,
I'm under impression that no one even tried to check manual proration functionality:
Once again: You are ordering inventory items from overseas and have to create an order and pay in $USD.
1. Please create simple 3 line purchase order for vendor (currency $USD). Your item cost include freight to one of the ports in Canada. Your freight company delivered goods to your warehouse and charged your for freight and other import charges in $CAD.
2. Process of items receipt. Now interesting part: Change to different vendor ($CAD) and add misc. charge, let say, brokerage prorated by relative value. Then for the same vendor add misc. charge freight that should be prorated manually (due to different item/weight cost). Go to each item "Allocated misc" field and try to enter your proration you calculated in advance. Good luck.
Dear Doug and tech support team, Do the requirement look unreasonable? Have you done above described steps? What can you say? Am I doing something wrong? Is software functioning properly? Do you have the recommendation how to complete above described transaction?
Regards Victor
_________________________
Victor
|
Top
|
|
|
|
#49618 - 04/14/16 07:53 AM
Re: Manual proration of MC in PO 9.2A
[Re: Victor B.]
|
Adagio Master
Registered: 03/16/99
Posts: 10504
Loc: Canada
|
Hello Victor,
Your impression is incorrect. We spent many hours in R&D and QA validating the various cost proration methods.
Please provide specific amounts for your example, and how you expect to see the costs allocated to the inventory items and COGS account. Only when we are discussing an actual example can we determine whether the program is functioning correctly.
_________________________
Andrew Bates
|
Top
|
|
|
|
#49624 - 04/15/16 08:54 AM
Re: Manual proration of MC in PO 9.2A
[Re: Victor B.]
|
Adagio Master
Registered: 03/16/99
Posts: 10504
Loc: Canada
|
Hello Victor,
Do we have a copy of this database so that we can make sure we are using the same configuration settings?
Have you placed the fields suggested by support on your Grid so you can see what's going on?
_________________________
Andrew Bates
|
Top
|
|
|
|
|
1872 Members
5 Forums
14528 Topics
70938 Posts
Max Online: 432 @ 01/20/25 10:17 PM
|
|
|
|
|
|
|