Hi,

I ran a gridview report for completed PO's and discovered incorrect information entered in a reference field on several of them. Is there a way to change those entries to the correct entry? (The field in question is the Reference field in Document Information)

Thanks
_________________________
Mike Smith
Viktorian Sheet Metal Mfg Inc

Top
#31920 - 05/22/12 09:35 AM Re: Changing information on a Completed PO [Re: MikeS]
Samuel Kopstick Offline
Adagio Maestro

Registered: 06/15/07
Posts: 942
Loc: GTA & North America (Remote Su...
I have never tried this before (never had to modify the Ref field after posting), but I just gave it a try in the POA Sample Data.

I find that I can change the Reference #’s on Completed P/O's, but not on the posted Receipts.

Is that what you are looking for?
_________________________
Samuel Kopstick
S Kopstick & Associates Inc
Toronto, ON

Top


Moderator:  Softrak Support 
Who's Online
0 registered (), 149 Guests and 3 Spiders online.
Key: Admin, Global Mod, Mod
Forum Stats
1868 Members
5 Forums
14580 Topics
71174 Posts

Max Online: 1408 @ 12/09/25 01:48 AM
January
Su M Tu W Th F Sa
1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30 31