In Company Profile, this option is set to "Net Item Cost".

When does the MRC get updated - when a PO is posted, or when a receipt is posted?

If memory serves me correctly, it used to be when a PO is posted or modified. But it seems that with this version it is when the receipt is posted.

Is there a setting that will allow the MRC to be updated when a PO is posted?

Steve

Joined: Nov 2001
Posts: 623
C
Adagio
Adagio
C Offline
Joined: Nov 2001
Posts: 623
Hi Steve,

Adagio PurchaseOrders will update IC Item Most Recent Cost at the following times:

- Purchase Order posted (only if IC Item has a $0 most recent cost)
- Receipt Posted - only if cost has changed
- Adjustment Posted - only if cost has changed

Hope this answers your question.


Chris McDonell
Softrak Systems Inc.

Moderated by  Softrak Support 

Link Copied to Clipboard
Who's Online Now
3 members (Dan_Desautels, Bruce Gardner, Douglas Dickie), 115 guests, and 3 robots.
Key: Admin, Global Mod, Mod
Forum Statistics
Forums5
Topics14,679
Posts71,626
Members1,874
Most Online1,408
Dec 9th, 2025
November
S M T W T F S
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30
Powered by UBB.threads™ PHP Forum Software 8.0.0